Project Description

  • Expected size: 52MW
  • Pre-concession obtained in September 2010
  • Feasibility studies were completed and approved by the Lao PDR government in 2013.
  • Environmental clearance obtained in 2013
  • Project Development Agreement signed in May 2014
  • Concession duration: 30 years including construction
  • The project was successfully divested to an Asian private investor in September 2015. The valuation agreed upon at pre-PPA stage confirms that the Group generates value through its project development capability.